| On 17 October 2010 memorial plaques were
unveiled at Lydney Docks and Purton as part of an anniversary remembrance of
the disaster on the night of Tuesday 25 October 1960 when the tankers
Arkendale H, laden with 300 tonnes of black oil and Wastdale H, carrying 350
tonnes of petroleum, collided on the Severn. On that night 16 vessels had made their way up river from both Avonmouth and Swansea but a thick fog descended on the river as they approached their destination of Sharpness. The Wastdale H had taken on its load of petrol at Avonmouth and was on a regular journey via the ship canal to Gloucester en route to Worcester. In the fog, the two tankers missed the dock entrance, collided and, locked together, were swept sideways upriver by the high tide and then demolished the 17th pier of the Severn and Wye Railway Bridge, sending two spans crashing into the water below. Leaking oil and gas from the 12" main carried by the 1879 built bridge caught alight and five of the eight men working on the tankers died. George Thompson, Skipper of the Arkendale and then aged 35, told the Citizen: "I jumped from the Arkendale over the flames and as I hit the water I heard an explosion. I jumped into thick black oil. The Wastdale was just one mass of flame. As I swam away a great perimeter of fire spread out following me all the time, just behind me. I don't know how long I was swimming but I know that I swam from one bank to the other." The two other survivors were James Dew, 43, from Burnham on Sea and Jack Cooper, also 43, from Cinderford. Jack Cooper was rescued by George Henderson and Tommy Carter, who went out into the burning river in a wooden boat. Lost in the tragedy were Herbert Dudfield, 46, from Corse, Alex Bullock, 40, Malcolm Hart, 17 and Percy Simonds, 35, all from Gloucester and Robert Niblett, 23, from Hardwicke. However, there was a lucky escape for those working on strengthening the bridge at the time, who had taken an early break in the signal box at Severn bridge station to the radio broadcast of a boxing match between Henry Cooper and Karl Muller. Had they still been working the death toll would have been much higher. Despite plans for rebuilding, the bridge was deemed too costly to repair in 1965. As such, the military were interested in demolishing the remaining structure as a training exercise with explosives but in the end the demolition contract went to Nordman Construction in 1967. Work started in September that year with a huge floating crane - Magnus II - being brought in from Hamburg. However, Nordman were not able to finish the job which was completed by Swinnerton and Miller in 1970. Some of the latter firm's work involved the former Aust to Beachley car ferry Severn King (Ian Hickman's 1/43 scale model of which is pictured above) used as a floating crane. Sadly though this vessel ran aground on one of the pier stumps and had to be scrapped. Today only the approach viaduct and swing bridge tower on the Sharpness side remain. | ||||
|
| ||||
|
| ||||
|
| ||||
| Work began on the Severn Railway Bridge
in 1875, the year before the Midland Railway opened a
branch line from Berkeley Road to serve the town of Berkeley and port of
Sharpness. The Severn & Wye Railway Company opened the 1 387' long
bridge on 17 October 1879. Designed by George William Keeling it had masonry
approach viaducts and 20 cast iron bow string spans 134' long and two spans
312' long. The bridge deck was 70' above high water and there was a
swinging section over the Gloucester and Sharpness Canal to allow tall ships
to pass through. Passenger services ran from Berkeley Road to Parkend but were cut back to Lydney in 1929. Freight traffic was abundant and the bridge was also used for diversionary traffic on winter Sundays when the 1886 Severn Tunnel was closed for engineering work. However, the Severn & Wye Railway never prospered and was taken over as a joint GWR and Midland concern with Midland maintenance and GWR locomotives. Locomotives of 65 tons or over were also banned. During World War II Vickers Wellington and other smaller aircraft were flown under the widest spans of the bridge and in 1955 strengthening work was begun to allow heavier trains. | ||||
|
| ||||
|
| ||||
|
Work on what would become the M4 ( later M48) Severn
Bridge began in 1961 and was completed on 8 September 1966 at a cost of
£ 8 million. In 2010 the tolls - applied just to get into Wales - were £5.50 per car and either £10.90 or £16.40 for larger vehicles. the crossing costs £12 million a year to run but on average collects £6 million a month. under the Severn Bridges Act of 1992, the bridge reverts to public ownership when £ 1 billion has been collected in tolls, valued at 1989 levels. This is expected to be in 2017. The M4 and M48 bridges are currently managed by Severn River Crossings plc. | ||||
|
| ||||